Works commence on site at Kingshott School.


 

T J Evers are pleased to work with Ball Hall Projects for the second time to construct a new sports hall at the Kingshott School in Hitchin.

The Scheme comprises the design and build of a new single storey sports hall and ancillary areas including a fitness suite, changing rooms, office, reception and a kitchen.

Only 8 weeks into the programme Evers have made a start on erecting the steel frame and will complete the structure in time for the cladding installation to begin early December.

 

Project Start Date: 25th September 2017  |   Project Completion Date: 11th June 2018  |   Value: £2.1 m

 

Project Team:

Anthony Fawcett – Site Manager

Justin Cooper – Contracts Manager

Kevin Howell – Quantity Surveyor