Works are progressing quickly at Queen Elizabeth School, Barnet.


Internally we have completed the underground drainage and cast in-situ ground floor slab is fully cast. The adjoining corridor to the new build has been erected and internal blockwork walls on the ground floor are almost complete.  First fix M&E works have also been carried out.

Externally, All glulam beams have been installed with tongue and groove roof decking ready for the Kalzip roof system. Face brickwork is also underway.

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 